St. Joseph's No Longer Largest Wind Project 25 November 09

wind turbineAt a November 2009 Manitoba Legislature crown corporations committee hearing Manitoba Hydro announced the proposed St. Joseph's wind project will be less than half its original size.

After a year long delay due to financial problems with the parent company Babcock and Brown, the Pattern Energy owned St. Joseph's wind project is going to produce only 138 megawatts of energy compared to the 300 megawatts originally planned.

St. Joseph's wind project was going to be the largest wind project in Canada and decrease in size will affect revenue for municipalities and landowners involved. The decrease in generation also effects Manitoba's goal of reaching 1000 MW of wind energy by 2015, since nine other licensed wind projects have been put on hold.

Pattern Energy is apparently looking to the Manitoba Government to subsidize the project, an act not all officials agree with. Manitoba Hydro says the power purchase agreement is almost complete.

View Manitoba Legislative Assembly Transcripts for Nov 17, 2009 (PDF)
View November 14, 2009 Winnipeg Free Press article
View November 18, 2009 Winnipeg Free Press article
View November 19, 2009 Steinbach Online.com press release
View Manitoba Wildlands' St. Joseph Wind Project webpage

Source: Winnipeg Free Press, Steinbach Online, Manitoba Legislative Assembly